West Row Apartments
Remove and Replace of Damaged Air Conditioning Systems
CTY Air was contracted to replace 45 Hail damaged air conditioning systems under an insurance contract.
The scope was to disconnect & remove systems from site, then once the damaged roofing had been replaced, supply & installation of 45 off Daikin Air Conditioning systems to serve the apartments throughout the building.
This project was delivered ahead of schedule by 3 weeks.
Client: KASE Building Group
Services: D&C of Mechanical Works
Project Value: $3M
Sector
Insurance
Location
Kingston, ACT
Year Completed
February 2021